HXTL (01085.HK): RMB 696,800,000 EPC Deal for Storage
NewTimeSpace News: On 23 November 2026, HXTL (01085.HK) issued a circular on a very substantial acquisition relating to the Shandong project and a notice of extraordinary general meeting. Zibo Longen Energy Co., Ltd., an indirect non-wholly-owned subsidiary, entered into an EPC contract for the project with the contractor after trading hours on 24 September 2026, at a total price of RMB 696,800,000, including RMB 69,814,300 of value-added tax.
The Shandong project is the Yiyuan Lucun Longen 200MW/800MWh electrochemical energy storage project in Lucun Town, Yiyuan County, Zibo, Shandong Province, together with a 220kV substation. The contractor must provide an irrevocable on-demand performance bond of 10% of the consideration, or RMB 69,680,000, within 15 days of the contract taking effect. Full-capacity grid connection is required within 148 calendar days from the commencement date, with completion acceptance targeted within 199 days.
The consideration will be funded by RMB 139,360,000 of internal resources (20%) and RMB 557,440,000 of external financing (80%) proposed to be obtained from Industrial Bank. The contractor was selected through a tender process and is a company incorporated in China in 2017 with registered capital of RMB 57.99 million, engaged in integrated energy services under the Inspur group.
As the highest applicable percentage ratio for the transaction exceeds 100%, it constitutes a very substantial acquisition under Chapter 14 of the Listing Rules and requires notification, announcement, a circular and shareholder approval. The Company will hold an extraordinary general meeting at 11:00 a.m. on 11 December 2026 in Admiralty, Hong Kong.